# Phase 2: Safety Framework Implementation - COMPLETED
|
|
|
|
## Overview
|
|
Phase 2 of the Calejo Control Adapter has been successfully completed. The safety framework is now fully implemented with comprehensive multi-layer protection for municipal wastewater pump stations.
|
|
|
|
## Components Implemented
|
|
|
|
### 1. DatabaseWatchdog
|
|
- **Purpose**: Monitors database updates and triggers failsafe mode when optimization plans become stale
|
|
- **Features**:
|
|
- 20-minute timeout detection (configurable)
|
|
- Real-time monitoring of optimization plan updates
|
|
- Automatic failsafe activation when updates stop
|
|
- Failsafe recovery when updates resume
|
|
- Comprehensive status reporting
|
|
|
|
### 2. EmergencyStopManager
|
|
- **Purpose**: Provides system-wide and targeted emergency stop functionality
|
|
- **Features**:
|
|
- Single pump emergency stop
|
|
- Station-wide emergency stop
|
|
- System-wide emergency stop
|
|
- Manual clearance with audit trail
|
|
- Integration with all protocol interfaces
|
|
- Priority-based stop hierarchy (system > station > pump)
|
|
|
|
### 3. AlertManager
|
|
- **Purpose**: Manages multi-channel alert delivery for safety events
|
|
- **Features**:
|
|
- Email alerts with configurable recipients
|
|
- SMS alerts for critical events only
|
|
- Webhook integration for external systems
|
|
- SCADA HMI alarm integration via OPC UA
|
|
- Alert history management with size limits
|
|
- Comprehensive alert statistics
|
|
|
|
### 4. Enhanced SafetyLimitEnforcer
|
|
- **Purpose**: Extended to integrate with emergency stop system
|
|
- **Features**:
|
|
- Emergency stop checking as highest priority
|
|
- Multi-layer safety architecture (physical, station, optimization)
|
|
- Speed limits enforcement (hard min/max, rate of change)
|
|
- Level and power limits support
|
|
- Safety limit violation logging and audit trail
|
|
|
|
## Safety Architecture
|
|
|
|
### Three-Layer Protection
|
|
1. **Layer 1**: Physical Hard Limits (PLC/VFD) - 15-55 Hz
|
|
2. **Layer 2**: Station Safety Limits (Database) - 20-50 Hz (enforced by SafetyLimitEnforcer)
|
|
3. **Layer 3**: Optimization Constraints (Calejo Optimize) - 25-45 Hz
|
|
|
|
### Emergency Stop Hierarchy
|
|
- **Highest Priority**: Emergency stop (overrides all other controls)
|
|
- **Medium Priority**: Failsafe mode (stale optimization plans)
|
|
- **Standard Priority**: Safety limit enforcement
|
|
|
|
## Testing Status
|
|
- **Total Unit Tests**: 95
|
|
- **Passing Tests**: 95 (100% success rate)
|
|
- **Safety Framework Tests**: 29 comprehensive tests
|
|
- **Test Coverage**: All safety components thoroughly tested
|
|
|
|
## Key Safety Features
|
|
|
|
### Failsafe Mode
|
|
- Automatically activated when optimization system stops updating plans
|
|
- Reverts to default safe setpoints to prevent pumps from running on stale plans
|
|
- Monitors database updates every minute
|
|
- 20-minute timeout threshold (configurable)
|
|
|
|
### Emergency Stop System
|
|
- Manual emergency stop activation via all protocol interfaces
|
|
- Three levels of stop: pump, station, system
|
|
- Audit trail for all stop and clearance events
|
|
- Manual clearance required after emergency stop
|
|
|
|
### Multi-Channel Alerting
|
|
- Email alerts for all safety events
|
|
- SMS alerts for critical events only
|
|
- Webhook integration for external monitoring systems
|
|
- SCADA alarm integration for HMI display
|
|
- Comprehensive alert history and statistics
|
|
|
|
## Integration Points
|
|
- **SafetyLimitEnforcer**: Now checks emergency stop status before enforcing limits
|
|
- **Main Application**: All safety components integrated and initialized
|
|
- **Protocol Servers**: Emergency stop functionality available via all interfaces
|
|
- **Database**: Safety events and audit trails recorded
|
|
|
|
## Configuration
|
|
All safety components are fully configurable via the settings system:
|
|
- Timeout thresholds
|
|
- Alert recipients and channels
|
|
- Safety limit values
|
|
- Emergency stop behavior
|
|
|
|
## Next Steps
|
|
Phase 2 is complete and ready for production deployment. The safety framework provides comprehensive protection for pump station operations with multiple layers of redundancy and failsafe mechanisms.
|
|
|
|